We have recently started the enabling works at Parkhead Health Centre for BAM Construction where we are carrying out drainage diversions on Salamanca Street whilst the demolition of the existing building takes places.

The works consist of installation of 375mm diameter drainage pipe, manholes, traffic management and tar re-instatement.

The main works are scheduled to start in the summer.

Dalcon demolition of existing building at Parkhead Health Centre

Installation of drainage diversion at Parkhead Health Centre

 

Dalcon installation 375mm diameter drainage pipe

Dalcon installation 375mm diameter drainage pipe

 

Dalcon enabling works at Parkhead Health Centre for BAM Construction

Installation of drainage diversion on existing tar road